21/07/18

Retweetd From HABE Sport

Thanks to everyone...students, parents and staff for a great year of sport see you in September! https://t.co/1DZjbJxQsa

19/07/18

DO YOU WANT THE CHANCE TO MAKE A DIFFERENCE? Do you want to make your voice heard and make a difference to the health services on offer to the Bromley community? If yes then why not join the Bromley Health Youth Forum! Find out more on our website Announcements page.

19/07/18

Innovation Day 3 - Some of the outstanding results from our student Bake Off today. Mr Castro certainly had a tough but tasty job of judging the entries! https://t.co/BoQxPV1vUA

19/07/18

Our French Trip has arrived in the UK safe and sound. Currently heading for HABE and traffic permitting still on schedule for 3.15pm pickup

19/07/18

HABE French trip 2018 en route to the UK. Estimated time of arrival 3.15pm at the Academy . Pick up point outside the Academy gates .

19/07/18

Innovation Day 3 - the HABE Bake Off begins! https://t.co/OY3tr5yeus

18/07/18

Innovation Day - Students study and enjoy street photography in London! https://t.co/uTh2N6F4vl

18/07/18

Our Harris Experience student's entry in the Christie's auction today won the highest bid at £340! Truly outstanding - Well Done!! https://t.co/g164TRYEPH

18/07/18

Our PE department ran a fantastic camping trip to Downe for our year 7 students. https://t.co/PDupkhDqKu

17/07/18

Innovation Day continues out and about with some of our students visiting the Windrush: Songs in a Strange Land exhibition at the British Library. A fascinating insight into the history of the Windrush story. https://t.co/X73PFMNj5N

17/07/18

The annual HABE French Trip! https://t.co/rSAlKEVPUn

17/07/18

The Stomp workshop is well underway starting with a demonstration from the professionals! Students will make their own upcycled percussion instruments and add movement later in the day https://t.co/86eTKEK0jW

17/07/18

Innovation Day - Y7-10 Emergency First Aid training now in progress! https://t.co/rPsO0Sr6l8

17/07/18

Innovation week has arrived at HABE! Educational trips, creativity, sports, scientific experiments and cooking to name but a few activities are filling the Academy for the next three days!

16/07/18

We are currently experiencing issues with our telephone system. We are trying to resolve this as soon as possible and apologise for any inconvenience caused.

14/07/18

Our arrival back to the Academy will now be the original time of 10pm! https://t.co/PDlgW6NVBd

14/07/18

🇪🇸 We have safely arrived at Heathrow airport. ETA to the Academy at this stage is 9:30pm, but will keep you informed if anything changes.

14/07/18

🇪🇸 Another fantastic day in Barcelona! Now sadly on our way to the airport. https://t.co/vdkRXO46ow

13/07/18

Exploring research methods in A level Psychology - 6th form taster day at HABE. https://t.co/HfBhsxIKV3

13/07/18

Sixth Form taster day - Breaking from traditional drawing methods our Y12 students are producing still life drawings of treasured and discarded objects. https://t.co/V7vFCXG5ss

Harris Academies
All Academies in our Federation aim to transform the lives of the students they serve by bringing about rapid improvement in examination results, personal development and aspiration.

Central Office

Bexley

Bromley

Croydon

Greenwich

Haringey

Merton

Newham

Southwark

Sutton

Thurrock

Wandsworth

Westminster

New Build Timeline

Link to New Build Timeline and Ariel Photo

 

August 2015

The new Harris Primary Academy is prepared ready for our new students.

Primary Academy Primary Acadamy Sign

September 2015

Temporary classrooms are almost completed, ready for the first phase of the development.  The DT, Art, Music and Business departments will be temporarily based here.

New build photo 21.9.15 2

The Academy grounds are now a hive of activity in preparation for the first phase of the move.

New build photo 28.9.15

October Half Term Break 2015

The first phase of the Academy's move towards our new build is taking place with Business, ICT, Art, Music and Design moving to our temporary accommodation.

Click to view the pictorial progress with the temporary accommodation

Start of the New Half Term November 2015

The students have already settled very well into the new classrooms.

New Cabins with Students Nov 15       New Cabins with Students Nov 15 2

December 2015

The beginning of the end of our original buildings!  Demolition of the old Sports Hall has started.

Demolition of Sports Hall - December 15

January 2016

Demolition of the old blocks continue and the path is cleared to accommodate the new entry road.

Jan 16  Jan 16 2

As the sun sets, we say goodbye to the old DT and Art block which has now  finally been demolished.

10.22.17.180_01_20160118164337249

Please click here to view a progress report from Kier

March 2016

The new build is progressing well, with three buildings now demolished. Since Christmas we have had over a thousand tipper lorries on site, removing soil and masonry. This, as you can imagine has been quite a logistical exercise, which has gone smoothly, with little impact on the local environment. All material removed from the site goes for recycling, giving the project 0% to land fill, a great achievement.

The concrete piles (which the building will sit on) for the primary academy are nearly complete, so the steel framing will start on time keeping the completion and handover in December 2016 for the Primary academy on target.

New Build Photo - March 16 (Insight)

May 2016

Exciting progress is being made with the arrival of the cranes.

New Build photo 12.5.16

May Half Term 2016

During half term, power sources will be redirected and with each day we can see more of the foundations being put into place.

Photo 27.5.16

June 2016

The concrete foundations are being laid.

photo 08.06.16 foundations being laid

 

July 2016

The foundations how now been put in place with exciting progress now accelerating week by week.

Photo1.7.16

Week Beginning 4th July 2016

The Building is beginning to rise from the foundations.

5.7.17

... First floor.

8.7.16

18.7.16

September 2016

The progress has continued during the Summer break and we are now entering our 12 month countdown with the official move to the new building still scheduled for August 2017.

........ Second floor.

31.8.16

....... And the third floor

Photo 19.9.16

Finally the roof and windows start to be put in place......

photo 28.9.16

Read HERE the latest update from Kier regarding the progress of our new academy.

October 2016

There is a hive of activity putting the roof in place.

05.10.16

November 16

During our half term break, the building has transformed with the windows now being put in place, making our new Academy water tight.

photo 28.11.16

January 2017

With the crane absent from the skyline and the building still on schedule to open in the summer, staff are very excited at the prospect of taking a first look inside, once the safety hats and boots have arrived! 

10.1.17

Read HERE the latest newsletter from Kier regarding progress of our new Academy.

February 2017

Whilst it seems that not much has progressed on the outside of our new Academy, we can confirm that inside it has been a hive of activity in preparation for our scheduled opening this summer - only 7 months away!

In the meantime the view from the second floor of our current building includes the new Primary Academy with the Construction Site offices serving as reminder of the work being carried out on our Academy.

027

And the lights illuminated our building in progress ...

photo 21.2.17

March 2017

With 6 months to go the scaffolding is being removed to reveal our new building and work is still progressing on schedule.

photo 2.3.17

Easter Break  - April 2017

The new primary stands completed and is now being enjoyed by all the primary students.

Primary Academy Finished - march 2017

Our Primary overlooks the ever progressing Secondary building.

Secondary Academy - March 2017

Since returning from Easter break and still on schedule with 5 months to go, we have for the first time been allowed to enter the new build to take our first photos of the internal space.

April 2017

IMG_4699

IMG_4712

PLEASE CLICK HERE TO VIEW FURTHER PHOTOS OF THE INSIDE OF OUR NEW BUILD

May 2017

The external finishing touches are apparent and in full progress.

May 2017

May 2017 finishing outside

Kier-Newsletter-June-2017

Almost ready to move in ...

July 2017 2July 2017 4