Close

Download our FREE smartphone app today!

Get the app

Twitter

15/06/18

Calling all HABE students! Don't forget to give Mr Wilkinson your completed Healthy Challenge Tracker by Monday lunchtime for a chance to be entered into the draw to win a £50 voucher to spend on any playground equipment of your choice! https://t.co/vkUN2xu8Pk

15/06/18

Pledges for a healthier lifestyle come flooding in from students and staff to conclude our Healthy Eating Week at HABE! Healthy facts, figures, activities and top tips to stay healthy have taken over the Academy all week and enjoyed by all. https://t.co/D9a5kDZHg3

15/06/18

Retweetd From HABE Sport

And they’re off..good luck to our Bronze DofE students!! https://t.co/CkmAjqKecB

14/06/18

Healthy Eating Week - activity challenge day! How any keepy-uppy's? We had plenty of entries which proves keeping active is fun! https://t.co/CrLVCnjSKM

14/06/18

Healthy Eating Week - Free sample smoothies on offer to staff and students - healthy and tasty! https://t.co/qcL45uORXC

14/06/18

HABE will remember the victims of Grenfell Tower today. https://t.co/GOPsTJTtJw

13/06/18

Healthy Eating Week continues with DRINK PLENTY! Today we are focusing on how important it is stay hydrated all day, drinking at least 6 to 8 drinks - did you know that water makes up about two-thirds of the weight of a healthy body! https://t.co/ZhU7bJGZ9t

12/06/18

It's free fruit Tuesday at HABE! - staff and students are given the opportunity to kick start their healthy five-a-day regime with a complimentary piece of fruit. Bananas, kiwi, pears, apples, oranges - free for all! #BNFHEW18 https://t.co/2qOwghn7be

11/06/18

Healthy Eating Week has started at HABE. Students can rise the challenges set every day and record their achievements all week. Today we are focusing on the importance of starting the day with a healthy breakfast! https://t.co/JgIpbSiQZV

08/06/18

Retweetd From HABE Sport

Starting the day off with a fantastic inspirational talk from resilience at its best! https://t.co/u9JCKBZXnP

08/06/18

Retweetd From HABE Sport

Trying kin-ball for the first time in the sports coaching session! https://t.co/T6dcfMgTfb

08/06/18

Retweetd From HABE Sport

The girls group brainstorming in the sports marketing session! https://t.co/f0Ua8m75Xo

08/06/18

Healthy Eating Week is coming to HABE next week! - keep watching to learn about the exciting healthy challenges our students can participate and achieve in. Who will win the individual challenge and a chance to win £50 of sports equipment for their year group? https://t.co/5Eu0hMu63A

08/06/18

Retweetd From HABE Sport

The Year 9 PE GCSE students have arrived for a day of sports science.

21/05/18

Our talented students have been demonstrating impressive skills and substantial developments with their beautiful sculptures. https://t.co/tX7eJ3shfU

15/05/18

All the staff at HABE wish our Year 11 students the very best of luck sitting their exams over the next few weeks.

07/05/18

Retweetd From HABE Sport

Superb weather to host the year 7 girls federation football tournament. Congratulations to everyone who participated this afternoon ⚽️ HABE teams finishing 2nd and 3rd place in a tense penalty shoot out! https://t.co/cMMhsa8REm

03/05/18

Excited HABE music students attended the Royal Albert Hall to enjoy a concert where the Royal Philharmonic Orchestra performed well known rock songs such as Queen's 'Bohemian Rhapsody', making these iconic tunes enjoyable and exciting for all age groups. https://t.co/kR2vFNialo

30/04/18

Our Year 11s working hard over the weekend at PGL Windmill Hill, focusing on English and Maths ahead of their upcoming exams. https://t.co/wWtAIxcWgC

30/04/18

Retweetd From HABE Sport

DofE Update: Congratulations to our students who completed their Bronze Practice Expedition today. Great resilience shown especially in challenging weather conditions

Harris Academies
All Academies in our Federation aim to transform the lives of the students they serve by bringing about rapid improvement in examination results, personal development and aspiration.

Central Office

Bexley

Bromley

Croydon

Greenwich

Haringey

Merton

Newham

Southwark

Sutton

Thurrock

Wandsworth

Westminster

New Build Timeline

Link to New Build Timeline and Ariel Photo

 

August 2015

The new Harris Primary Academy is prepared ready for our new students.

Primary Academy Primary Acadamy Sign

September 2015

Temporary classrooms are almost completed, ready for the first phase of the development.  The DT, Art, Music and Business departments will be temporarily based here.

New build photo 21.9.15 2

The Academy grounds are now a hive of activity in preparation for the first phase of the move.

New build photo 28.9.15

October Half Term Break 2015

The first phase of the Academy's move towards our new build is taking place with Business, ICT, Art, Music and Design moving to our temporary accommodation.

Click to view the pictorial progress with the temporary accommodation

Start of the New Half Term November 2015

The students have already settled very well into the new classrooms.

New Cabins with Students Nov 15       New Cabins with Students Nov 15 2

December 2015

The beginning of the end of our original buildings!  Demolition of the old Sports Hall has started.

Demolition of Sports Hall - December 15

January 2016

Demolition of the old blocks continue and the path is cleared to accommodate the new entry road.

Jan 16  Jan 16 2

As the sun sets, we say goodbye to the old DT and Art block which has now  finally been demolished.

10.22.17.180_01_20160118164337249

Please click here to view a progress report from Kier

March 2016

The new build is progressing well, with three buildings now demolished. Since Christmas we have had over a thousand tipper lorries on site, removing soil and masonry. This, as you can imagine has been quite a logistical exercise, which has gone smoothly, with little impact on the local environment. All material removed from the site goes for recycling, giving the project 0% to land fill, a great achievement.

The concrete piles (which the building will sit on) for the primary academy are nearly complete, so the steel framing will start on time keeping the completion and handover in December 2016 for the Primary academy on target.

New Build Photo - March 16 (Insight)

May 2016

Exciting progress is being made with the arrival of the cranes.

New Build photo 12.5.16

May Half Term 2016

During half term, power sources will be redirected and with each day we can see more of the foundations being put into place.

Photo 27.5.16

June 2016

The concrete foundations are being laid.

photo 08.06.16 foundations being laid

 

July 2016

The foundations how now been put in place with exciting progress now accelerating week by week.

Photo1.7.16

Week Beginning 4th July 2016

The Building is beginning to rise from the foundations.

5.7.17

... First floor.

8.7.16

18.7.16

September 2016

The progress has continued during the Summer break and we are now entering our 12 month countdown with the official move to the new building still scheduled for August 2017.

........ Second floor.

31.8.16

....... And the third floor

Photo 19.9.16

Finally the roof and windows start to be put in place......

photo 28.9.16

Read HERE the latest update from Kier regarding the progress of our new academy.

October 2016

There is a hive of activity putting the roof in place.

05.10.16

November 16

During our half term break, the building has transformed with the windows now being put in place, making our new Academy water tight.

photo 28.11.16

January 2017

With the crane absent from the skyline and the building still on schedule to open in the summer, staff are very excited at the prospect of taking a first look inside, once the safety hats and boots have arrived! 

10.1.17

Read HERE the latest newsletter from Kier regarding progress of our new Academy.

February 2017

Whilst it seems that not much has progressed on the outside of our new Academy, we can confirm that inside it has been a hive of activity in preparation for our scheduled opening this summer - only 7 months away!

In the meantime the view from the second floor of our current building includes the new Primary Academy with the Construction Site offices serving as reminder of the work being carried out on our Academy.

027

And the lights illuminated our building in progress ...

photo 21.2.17

March 2017

With 6 months to go the scaffolding is being removed to reveal our new building and work is still progressing on schedule.

photo 2.3.17

Easter Break  - April 2017

The new primary stands completed and is now being enjoyed by all the primary students.

Primary Academy Finished - march 2017

Our Primary overlooks the ever progressing Secondary building.

Secondary Academy - March 2017

Since returning from Easter break and still on schedule with 5 months to go, we have for the first time been allowed to enter the new build to take our first photos of the internal space.

April 2017

IMG_4699

IMG_4712

PLEASE CLICK HERE TO VIEW FURTHER PHOTOS OF THE INSIDE OF OUR NEW BUILD

May 2017

The external finishing touches are apparent and in full progress.

May 2017

May 2017 finishing outside

Kier-Newsletter-June-2017

Almost ready to move in ...

July 2017 2July 2017 4

July 2017 3